Sheffield bridge replacement to affect rail journeys this weekend
A 73-tonne deck will be lifted into place over the River Sheaf at Beauchief, while Dore & Totley station’s platforms and car park are affected.

Rail passengers in Sheffield face changes to some journeys this weekend, 7-8 November, while Network Rail replaces a bridge deck over the River Sheaf at Beauchief. The work will also make both platforms at Dore & Totley station inaccessible for the weekend.
The railway bridge carries trains over the river. Network Rail says its steel structure has reached the end of its service life and must be replaced to keep the railway operating safely. The main operation is to lift a new 73-tonne deck into position by crane.
The work is part of a wider upgrade: rail will be renewed, with 90 new sleepers and 86 tonnes of ballast. Network Rail says the project is expected to be completed by early December, when the Dore & Totley station car park is also due to be fully restored.
What passengers need to know
Network Rail says some services will be amended over the weekend, but the specific service changes are not set out in its announcement. Passengers are advised to check their journey with their train operator or National Rail before setting off, and to allow extra time where needed.
Dore & Totley station’s car park has been used as a project compound during preparation work. Alternative parking is available at Abbeydale Badminton Club, behind Abbeydale Sports Club. Accessible drop-off and pick-up points have been provided at Ladies Spring Grove. Both station platforms have remained open during preparation but will not be accessible this weekend.
Why the work was rescheduled
The deck lift was postponed in March to protect passenger services after delivery of a specialist wagon needed for the project was delayed. Network Rail lead portfolio manager Tom Grainger said the replacement would support safe and reliable railway operation for decades. He apologised for asking passengers to change travel and parking plans for a second time.
Train operators said they are working with Network Rail and putting alternative travel arrangements in place, but did not provide details of those arrangements in the announcement. The project team has not stated when the station platforms will reopen after the weekend; the announced completion target for the project and car park restoration is early December.
This report draws on information from Network Rail Media Centre.